Determination in construction contracts
The term ‘determination’ in relation to construction contracts typically relates ending the contractor’s employment under the contract. Contracts may provide for determination of the contractor’s obligations under the contract by the employer or the contractor if there is a breach of contract by the other party. This may happen if one of the parties has ceased to perform their obligations under the contract, for example, if the contractor is no longer proceeding regularly and diligently with the works. However, the contract itself remains in place, and so do the rights of both parties.
This is as opposed to the termination of the contract, which brings the contract itself to an end. This may happen, for example, if one of the parties to the contract behaves in such a way that it indicates it no longer intends to accept its obligations under the contract, this is considered to be a repudiatory breach (or fundamental breach) allowing the innocent party to terminate the contract and to sue for damages.
For more information, see Repudiatory breach in construction contracts and Termination.
The word determination may also refer to determining the outcome of an assessment, such as expert determination, determination of approval for building regulations applications or planning applications and so on.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.